Construction

Waterproof construction is the key to the waterproof project. According to the survey, the leakage caused by improper construction is up to 80%. In order to solve this problem, Landun implements standardized construction management for the purpose of universal, but not targeted standardization is not a real standardization. From the outfits of workers to technological process, foundation to detailed nodes, Landun strives to excellence in construction by closely combing the versatility with relevance. .



General engineering methods

1. Pre-anti-sticking method

Pre-reverse anti-sticking method: pave the waterproof roll covered with polymer self-adhesive layer in the foundation surface, and then pour the concrete structure, so that the concrete slurry closely connects with the membrane adhesive layer.



Process
* Foundation cleaning: clean debris and dust and remove protrusions on the foundation;
* Positioning & line snapping: According to the work face condition, first snap the first positioning line, and the distance of the second and the first is the width (1m) of a roll. The following baseline is all 0.93m away from the previous baseline for line snapping and positioning. After paving baselines, unfold the roll and adjust the alignment baseline to ensure rolls to be paved flatly;
* Details node waterproof: first conduct reinforcement treatment on pile heads, post-cast strips and other nodes.
* Roll pavement: first according to the baseline laying of the first roll, and then laying a second, and then opened two long membrane lap joints isolation film, the long side lap, lap width 70mm, short side with adhesive tape lap, lap width of 80mm. Before lap, first with a brush to clean the area overlap floating sand, adhesive tape and shop pavement, and then paste the upper roll, the lap will be repeatedly pressed with roller pressure roller to ensure that the waterproof layer Continuity and integrity.





Precautions
* Pre-reverse anti-stick construction method, the roll should be a single layer laying;
* When laying in the wet foundation surface, the foundation surface should be strong and free of water;
* Facade construction, self-adhesive edge position within 10 ~ 20mm from the edge of the membrane should be mechanically fixed at intervals of 400 ~ 600mm, and should ensure that the fixed position is completely covered by the membrane.



2. Coating & membrane composite construction technology

Coating composite method is the use of CPC non-bitumen-based non-curable rubber waterproof coating and CPC non-bitumen durable reaction-based self-adhesive waterproof membrane composite construction process.



Process
* Foundation cleaning: clean debris and dust and remove protrusions on the foundation;
* Foundation treatment: generally, the coating can be directly carried out after cleaning the foundation, and when necessary, the shot blasting can be carried out.
* Heating CPC non-asphalt-based non-curing rubber waterproof coating: put the paint in the dekeer or heating equipment;
* Detailed node waterproof: first conduct reinforcement treatment on the corner, pipe root, water mouth, deformation joint and other nodes;
* Positioning & line snapping: According to the work face condition, first snap the first positioning line, and the distance of the second and the first is the width (1m) of a roll. The following baseline is all 0.92m away from the previous baseline for line snapping and positioning.
*Trial paved roll: after drying the foundation treatment agent, unfold the self adhered roll on the foundation surface, and fold it back after positioning;
*CPC asphalt based curing rubber waterproof coating construction: the heating of the CPC asphalt based curing rubber waterproof paint into the bucket, pour on the surface, in accordance with the scope of the CPC non elastic line pitch based curing rubber waterproof paint is coated on the surface, coating thickness, the bottom is not exposed;
* paving rolling material: before the coating is cooled, remove the surface isolation film under the self adhesive material and paste the rolled material on the coating.





Precautions
* After the coating is scraped, it is appropriate to put up the material or isolation layer immediately to prevent the adhesive from affecting the stickup.
* When the material of the matrix is added, it should be put up before the coating is cooled, and the coating can be carried out immediately after the paving is completed.
* When the additional layer is constructed, the reinforcement of the matrix should be laid.
* When coating and roll composite waterproof construction, it should be laid before the coating is cooled. The lap joints are bonded by hot melt coatings and sealed with hot melt coatings.



3. Wet paving method

Wet paving method is mainly for the construction technology of CPC non asphalt based durable polymer self-adhesive waterproof membrane, and its principle is to use cement slurry to achieve effective bonding between roll and base.



Process
* Foundation cleaning: clean debris and dust and remove protrusions on the foundation;
* Preparation of cement slurry: first pour the water into the mixing barrel, then immerse the cement in the water according to the weight of cement: water =2:1; drain the excess water and stir it with electric mixer to make it putty.
* Detail waterproof: first conduct reinforcement treatment on the corner, pipe root, water mouth, deformation joint and other nodes before paving rolls and treat them with special sealants; * Positioning, line snapping & trail pavement: Positioning and line snapping as above described. After paving baselines, unfold the roll and adjust the alignment baseline to ensure rolls to be paved flatly;
*Turn back and tear off the isolation membrane: after the test is finished, one end of the roll is lifted and the back is turned back to the other end. With a paper knife in the roll at the fold and cut off isolation film;
* Coat and scrape cement: all the rolls and foundation surfaces need to be scraped and coated with cement slurry once again. The coated and scraped cement paste should be even and smooth, and the width of the coating and scraping will be 100mm wider than that of the rolls.
* Roll paving: one end of the roll is coated with cement slurry to lift back and paved on the foundation surface, with a rubber scraper or roller from the middle to both sides to exclude air blowing pressure, enabling the roll to fully adhere to the foundation surface, the cement slurry scraping pressure discharged back scraping edge, the other end is coiled on the same method for paving treatment.





Precautions
* If the ambient temperature is too high, cold water can be drenched on the surface of the membrane in order to tear apart the isolation membrane.
* Because this product has good bonding performance, it is difficult to recover once the crosslinking is formed. Therefore, the builders need to do a good job of planning, and should try to make a success as much as possible to avoid the inconvenience caused by repeated construction.



Detailed nodes



Waterproof structure of roof deformation joint (innovative practice)

1.Cut grooves on both sides of the deformation joint and inject glue in the grooves
2.Brush chloroprene rubber to temporarily fix PVC roll waterstop
3.Splice the waterstop in the seams
4.Install the prefabricated concrete cover after adding polyethylene polypropylene isolation layer at the deformation seam

Waterproof structure of roof deformation joint (conventional practice)

1.Making a circle by cement paste, radius more then 50mm
2. Waterproof additional layer construction, the width is 500mm
3. Construction of large area waterproof layer
4. Construction of waterproof additional layer
5. Waterproof membrane cover
6. installation of deformation and seams of galvanized steel plate

Roof gutter waterproof construction

1.Construction of waterproof additional layer, the width of additional layer should not be less than 250mm
2.Construction of large area waterproof layer
3.The cement nail is fixed with the roll, and the special sealing paste is applied to the joint.

Construction method for waterproof roofing parapet wall

1.The radius of the reverse arc of cement mortar is not less than 50mm
2.The construction width of the waterproof additional layer is 500mm
3.Construction of large area waterproof layer
4.Cement nails and layering roll in the groove back into the parapet
5.Paint waterproof node seal ointment

Waterproof structure of back pouring belt in basement floor

1.Waterproof additional layer construction, each extension 250mm on both sides of the backwards.
2.Construction of large area waterproof layer
3.Floor concrete pouring

Waterproof practice at the intersection of basement floor and side wall

1.The radius of the reverse arc of cement mortar is not less than 50mm
2.Construction of large area waterproof layer
3.Fix rolls on the protective wall and set up temporary protection
4.concrete pouring floor concrete

Underground engineering and the exterior angle at the roof waterproof construction practices

1.Cement mortar inverted circular arc, the radius is not less than 20mm
2.The auxiliary layer at the angle of the sun is constructed, the width is 500mm
3.Construction of large area waterproof layer
4.Fine stone concrete protection layer

Underground engineering side wall construction joints waterproof practices

1: Waterproof additional layer construction, a width of 500mm
2: Construction of a large area waterproof
3: Basement sidewall protection layer construction

Shenzhen Lan Dun Holding Co. Ltd.
Address:7th Floor, Block 2, Fangda City Building, No.2 Longzhu Fourth Road, Nanshan, Shenzhen, Guangdong, China
Phone:0755-82932808 Fax:0755-82932208
E-mail:[email protected]


National hotline:400-678-2433

Follow our official Wechat

123内部透码